New Town Hall Construction Project

new Town Hall building

7/15/2021 - It's been almost two years since our first post for this project, and now we are so pleased to be able to say that the New Town Hall Construction Project is complete!  The final time-lapse video shows the completion of the parking lot and installation of landscaping.image showing permeable paver parking lot

Want to see it all again? Richmond Time Lape has posted a playlist with all of the videos from start-to-finish, or if you want it all a single video, click here! Better still, stop by and see the completed project in person - Town Hall is open Monday-Thursday from 7:30am to 6:00pm, and the Ashland Farmers market takes place in and around the new parking lot on Saturdays from 9:00am to 12:00pm.


5/6/2021 - Once demolition was complete, it was time to start the final phase of the project - the parking lot! When compled, this permeable paver lot will not only manage stormwater and provide extra parking for the downtown area, but will also be home to the Ashland Farmers Market. Check out the time-lapse video to see the progress thus far, with completion of the lot expected by the end of the month.


2/22/2021 - Demolition of the Old Town Hall took place in January, and it happened fast! It happens even faster in January's time-lapse video, but the clean-up and earth-moving operations are mesmerizing to watch.

2/9/2021 - September time-lapse video shows the creation of the front walkway.

1/5/2021 - We have been in the building since November, but here's a throwback time-lapse video, going back to August. You may need to watch it twice, once for the work and once for the clouds!

10/5/2020 - We are in the home stretch!

New Town Hall

7/15/2020 - As we enter the final few months of construction, more work is moving inside, but the columns are completed and boxes appear on the roof in the time-lapse video for June.

6/26/2020 - Columns going up and lots of digging for underground utilities in May’s time-lapse video

5/19/2020 - In April’s time-lapse video, some of the work has moved inside, but exterior architectural details are starting to take shape.

4/24/2020 - March time-lapse video - the brick facade is completed, more layers are added to the roof, and glass installation gets underway!

4/16/2020 - February’s time-lapse video has much to see - watch the dormers taking shape, the brick facade start to go up, and additional roof layers being added. The cranes are mesmerizing!

4/15/2020 - Roof panel installation begins in January’s time-lapse video

1/28/2020 - Steel roof ridge and rafter beams are lifted into place by crane in December’s time-lapse video

12/20/2019 - Time-lapse video for November - start of second level construction and walls

12/10/2019 - Steel beams go up in the time-lapse video for October! 

10/9/2019 - Check out the time-lapse video of the construction work done during the month of September!

10/3/2019 - The construction of the new Town Hall building is underway! The foundation has been completed, and the stairwell and elevator shaft have been completed. The concrete slab for the first floor will be poured early this month, then the structural steel members will be erected, and we will begin to see the outline of the building.

new town hall construction site

9/16/2019 - Check out a time-lapse video of the construction work done during the month of August!

7/19/2019 - Effective 7:00 am on Friday, July 19, 2019 Duncan Street behind Town Hall will be closed and temporary fencing will be erected for the duration of the New Town Hall Construction Project. While both public entrances to Town Hall will remain open, the accessible entrance facing Duncan Street will only be able to be reached from the north end of the building (i.e. the sidewalk from Thompson Street).

Ashland Town Hall - Temporary Fencing Layout